T25KCB
Manufacturing Consultant and Executive Coach
Automotive
Launch Manager
Project Length
-
12 Months
Objective
-
Ensure the successful launch of L551
Issues to start with
-
3 Major projects started at the same time + Transfer of existing IP assembly to new AGV line & plant
Plan to fix it
-
Supported Programme Management in the Implementation of L551 Armature and Console Assemblies into new Manufacturing Facility.
-
Supported on the line L551 pre-production builds T1 & T2.
-
Held daily project meetings with Manufacturing Launch Team.
-
Updated, Reported and Monitored on project status weekly/ Monthly with SLT.
-
Attended and contributed regularly to DFM & DFA activities with JLR.
-
Attended and presented at monthly meetings with JLR Supply Chain Management.
-
Issues on the way
-
Introduction of AGV line for existing models was taking up all the resource's
Result
-
L551 T1 & T2 Builds Completed Successfully
Senior Project Manager
Project Length
-
6 Months
Objective
-
Identify and Implement Cost Reduction Programmes Cross Car Line JLR
Issues to start with
-
Vehicle costs & Kg's were much higher than competitors vehicles
Plan to fix it
-
Identified and developed cost-saving opportunities on materials across D8, D7U and D7A vehicle platforms,
-
Carried out one to one reviews to explore possible cost saving opportunities with the Should Be Cost Engineers
-
Developed a product-focused outlook to line walks, emphasis being on quality rather than quantity of ideas, endorsed a small team approach.
-
Organised one to one Plant line walks at FA2, Halewood and Castle Bromwich
-
Recorded opportunities on to company wide portal
Issues on the way
-
Reluctance by Design Engineers to consider changes to their designs.
-
Being able to engage with C of E managers on savings which equated to less than £60k per annum
Result
-
Spearheaded £5M per annum in cost savings by setting up a system to track the progress of cost-reduction ideas in iHopper and CCR at various milestone stages.
Launch Manager
Project Length
-
6 Months
Objective
-
Defining of process steps to build Front and Rear seats for the New Mini Project for BMW.
Issues to start with
-
New project for a New Customer in the UK
Plan to fix it
-
Attend regular core team meetings in Munich.
-
Work closely in Bad Abbach with Process and Design Engineers to ensure design for manufacture.
-
Produce Preliminary Process Flows & FMEA's
-
Simulate complete build using edited video
-
Introduced Faurecia best practices into Production Process
Issues on the way
-
Fine tuning of manual processes to avoid RSI Issues
Result
-
Initial build phases completed in time to meet Industrialisation start date
Launch Manager - Seating
Project Length
-
16 Months
Objective
-
Ensure ZS44, ZM44 & ZS 44 Projects for Nedcar were launched on time
Issues to start with
-
Factory set up in Holland as a brownfield site
-
Management and Staff were being transferred from an Exhaust Plant to start up a seating plant
Plan to fix it
-
Develop and introduce KPI’s for monitoring Project Status.
-
Introduce visual management system to track Project Progress.
-
Introduction of autonomous cells into manufacturing.
-
Coach and mentor New management team in Faurecia Excellence System, Production System Efficiency and Employee Empowerment.
Issues on the way
-
Employees from Exhaust plant didn't have the dexterity to build seats
Result
-
Successful launch of 3 projects
Launch Manager - Seating
Project Length
-
3 Months
Objective
-
Ensure MCC Project for Daimler Chrysler adhered to Customers timing.
-
Implement best practice lean principles
Issues to start with
-
Location Pierrepont, Eastern France
-
Language barrier
-
Different cultures
Plan to fix it
-
Industrial Planning of logistics/ warehouse to reduce stock and resources.
-
Implementation of a small train and small box to reduce line side stock.
-
Industrial planning and the introduction of a flow line from a modular seating build
Issues on the way
-
Continued resistance from Management
Result
-
Flow line and Lean principles adopted in to manufacturing cell
Production Manager - Seating
Project Length
-
4 Months
Objective
-
Responsible for all aspects of production management & control
Issues to start with
-
High Absenteeism
-
Running on 2 Shifts
-
Unable to achieve customer run at rate criteria
-
Poor right first time
Plan to fix it
-
Monitor productivity & achievement of targets against key objectives
-
Co-ordinated production planning & production scheduling activities
-
Introduce controls to reduce absenteeism
-
Recruit & train 3rd shift
-
Create measles chart to target hot spot quality issues first
Issues on the way
-
Having to play catch up on lost production during the week
Result
-
Absenteeism reduced from 15% to 4%.
-
Run at rate achieved
Launch Manager - Interior Trim
Project Length
-
18 Months
Objective
-
Industrialise New Injection Moulded Products and Assemblies for Corolla & Avensis in the UK
Issues to start with
-
Low Pressure back injection was a new process to Fradley
Plan to fix it
-
Buy Off Tooling and Assembly processes in Europe & Japan.
-
Liase between Development in Meru and Fradley
-
Ensure Product Validation is achieved
-
Capacity Planning for 13 Injection Moulding Machines
-
Capital Justification and purchase of Special Purpose Equipment.
-
Introduce dedicated resource to develop & Industrialise Low Pressure Back Injection process.
Issues on the way
-
Developing Tooling and Products to ensure successful de-mounting of parts with robots
-
Tuning processing conditions to optimise the process.
Result
-
Products successfully launched into serial Production.
Production Manager - Interior Trim
Project Length
-
12 Months
Objective
-
Transfer production from Germany supplying UK customers to a UK location
Issues to start with
-
Factory set up in UK as a greenfield Site
-
Introduce new In Mould Decoration Technology
Plan to fix it
-
Develop Organisational Structure, Reporting Lines & Job descriptions
-
Establish departmental procedures & standards for ‘best practice’
-
Recruit a well balanced team of 72 staff including key managers
-
Handle training & career development for senior team members
-
Manage budgets, forecasting, purchasing & stock control activities
-
Control scheduling & production planning, job cards & costings
-
Use RFT for defect analysis & Tops 8D for root cause analysis
-
Ensured efficient deployment of staff to maximise available resources
Issues on the way
-
Troublesome supply of soft painted parts to plant.
-
Difficulty transferring Cup holder design to go into a serial production assembly.
Result
-
Transfer complete