T25KCB
Manufacturing Consultant and Executive Coach
Aerospace
Delivery Assurance
Project Length:
-
18 Months
Objective:
-
To achieve on-time deliery in full with multiple strategic suppliers operating in the UK and Europe.
Issues Prior:
-
Material shortages and delays causing manufacturing line stops
-
Delivery schedule at 60% on time delivery (not even in full)
Plans to Resolve:
-
Chaired regular meetings to encourage constructive communication between client and suppliers
-
Re-educate supplier to utilise client supplier portal
-
Monitor production process stages weekly using WIP Tracker
-
Implement corrective action process for any issues
Issues During:
-
Supplier stakeholder’s reluctance to change
-
Supplier blaming client
-
Resource shortage within suppliers
Outcome:
-
On average 12 week turn around with each supplier
-
Line stops eliminated
-
90% on time delivery in full
-
100% adherent to usage of supplier portal
-
Vast improvements to client and supplier relationships
Manufacturing Manager
Project Length
-
3 Months
Objective
-
Increase OTDIF and Improve customer satisfaction
Issues to start with
-
Shop floor managed by fire fighting
-
No targets for completing work packages
-
Supervision lacked leadership
-
HIghly skilled manual intervention
Plan to fix it
-
Developed and implemented a Dashboard in collaboration with the IT department, enabling the monitoring and reporting of production and non-production hours vs attendance hours.
-
Introduced a visual management approach to shop floor production scheduling
-
Implemented a daily report to monitor Actual Sales vs Target, as well as corrective actions to reduce potential slippage.
Issues on the way
-
Resistance from Shop floor supervision
Result
-
A reduction in lost time hours to less than 4%.
-
Increase in productivity
-
Deliveries to customers improved eliminating Line Stops
Project Manager – Off-Load Programme
Project Length
-
3 Months
Objective
-
Ensure continuity of deliveries on 7 NPI projects for various OEM's during the Offloading of production from Camberley
Issues to start with
-
Goods Inward/ Dispatch not set up for cross-docking of materials to sub-suppliers.
-
Resources were already stretched trying to maintain supply to the OEM's
-
Scope of works for sub con not clearly defined.
-
No resource Identified at the supplier to manage deliveries
-
Delivery Assurance contractors in suppliers reported on status. Not held accountable for Implementing solutions
Plan to fix it
-
Finalised the transfer of tools and materials for 7 Aerospace projects from Camberley to the UK, Europe and Mexico for suppliers to achieve OTDIF.
-
Collaborated with Supply Chain Personnel from Boeing to ensure continuity of deliveries.
-
Conducted accurate and efficient weekly reporting to SLT on Transfer Of Work progress.
Issues on the way
-
Employees working in Silo's
Result
-
Improved collaboration between Logistics, Purchasing and Sub Con
-
Transfer of Project to Mexico achieved.
-
Developed, Implemented & carried out plans with Sub Contractors to achieve OTDIF
Operations Programme Manager – Actuation
Project Length
-
6 Months
Objective
-
Ensure MC21 Iron Bird & AC 1 were completed on Time.
Issues to start with
-
Shortages of Gears form Manufacturing Cell
-
Shortages of parts from Suppliers
-
Difficult to formulate a resource plan based on Single Shift due to sporadic supply of parts
Plan to fix it
-
Produce MPS for Assembly of Slats Flaps & Transmission Shafts
-
Generated resource and training plan in line with MPS, to meet demand.
-
Reduced delays to the build plan by ensuring the timely completion of concessions, coordinating with engineering teams.
-
Secured shared resources to meet the build plan, liaised with department heads, and coordinated with the Verify team to ensure the prompt approval of Supplier FAI’s to meet MPS.
-
Performed Production Process monitoring against plan.
-
Monitored Supply Chain Deliveries against production plan through LOB.
-
Implemented a resource plan to cover 24 hour assembly of Actuators.
Issues on the way
-
C Series Gear Manufacture was taking priority over MC21